Question

Ted can complete a work in 8 days working 12 hours a day. Sid can complete the same work in 16 days working 5 hours a day. If both Ted and Sid work together, working 6 hours a day, in how many days can they complete the work?


A

80/11

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B

61/11

No worries! We‘ve got your back. Try BYJU‘S free classes today!
C

71/11

No worries! We‘ve got your back. Try BYJU‘S free classes today!
D

72/11

No worries! We‘ve got your back. Try BYJU‘S free classes today!
E

None of these

No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A

80/11


Ted can complete the work in (8×12) hrs = 96 hrs
Sid can complete the work in (16×5) hrs = 80 hrs
Ted's 1 hour's work =196 and Sid's 1 hour's work =180
(Ted + Sid)'s 1 hour's work =(196+180)=11480
So, both Ted and Sid will finish the work in (48011) hrs
Number of days 6 hours each =(48011×16)=8011 days = 7311 days


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Speed-Distance-Time
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon