Ten men, working for 6 days of 10 hours each, finish 521 of a piece of work. How many men working at the same rate and for the same number of hours each day, will be required to complete the remaining work in 8 days?
Work done =521
Remaining work =1−521=1621
521 of a work can be done in 6 days working 10 hours a day by = 10 m
1 work can be done in 6 days working 10 hours a day by =10×215
1 work can be done in 1 day working 10 hours a day by =10×21×65 men
1621 work can be done in 8 days working 10 hours a day by =10×21×6×165×21×8=24 men