A and B can do a piece of work in 20 days and B in 15 days. They work together for 2 days and then A goes away. In how many days will B finish the remaining work?
Open in App
Solution
Step 1 : Find the remaining work
Given : A and B can do a piece of work in 20 days.
B can do a piece of work in 15 days.
They work together for 2 days and then A goes away
Amount of work done by A and B in 1 day =120
Amount of work done by B in 1 day =115
A and B work together for 2 days .
Work done by them in 2 days =2×120=110
Remaining work =1−110=10−110=910
Step : 2 Time required by B to finish the remaining work
Time required by B to finish the remaining work =910115
=13510
=1312days
Hence, B can finish the remaining work in 1312 days.