Question
Directions: The following items consist of two statements; one labeled as 'Statement (I)' and the other as 'Statement (II)'. You are to examine these two statements carefully and select the answer to these items using the codes given below:
Statement (I): A linked-bar chart is premised on a resource-based scheduled network, and so it is unique to the relevant project.
Statement (II): A squared scheduled network drawn after allocating activity durations, with consideration of originally available floats, may yet have the inputs-scheduling pending.