Question

The amount of work done in moving 2.5 C charge over a potential difference 330 mV is:

A
132 mJ
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
415 mJ
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
1650 mJ
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
825 mJ
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 825 mJ
Given,
Charge (q) = 2.5 C
Potential difference (V) = 330 mV

We know,
work done (W) = q x V
So, W = 2.5 C x 330 mV = 825 mJ (as 1 C x 1 mV = 1 mJ ).
Thus, the correct answer is option d.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Initial Evidence of Current Electricity
PHYSICS
Watch in App
Join BYJU'S Learning Program
CrossIcon