CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

The arc lengths of a directed graph of a project are as shown in the figure. The shortest path length from node 1 to node 6 is


  1. 7

Open in App
Solution

The correct option is A 7
Shortest path is



Shortest length = 7

It is the problem of the shortest path which will be 7.

In this question do not confuse with critical path.

Examiner asks for the shortest path. Critical path is the longest path which is not asked in this question.

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Cartesian Plane and Coordinate Axes
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon