The arc lengths of a directed graph of a project are as shown in the figure. The shortest path length from node 1 to node 6 is


  1. 7

Open in App
Solution

The correct option is A 7
Shortest path is



Shortest length = 7

It is the problem of the shortest path which will be 7.

In this question do not confuse with critical path.

Examiner asks for the shortest path. Critical path is the longest path which is not asked in this question.