Question

the estimated percentage break-up of the cost of construction of a house (excluding cost of land) is as follows:
Labour Bricks Cement Steel & Timber Marble Miscellaneous
20% 12% 25% 15% 13% 15%
Construct a pie diagram to represent the given data.

Open in App
Solution

The percentage values are converted into degree values using the following formula.
Degree share= Percentage share100×360 = Percentage share ×3.6
Items Expenditure
(in percent)

Degree Share
Labour
Bricks
Cement
Steel and timber
Marble
Miscellaneous
20
12
25
15
13
15
20 × 3.6 = 72°
12 × 3.6 = 43.2°
25 × 3.6 = 90°
15 × 3.6 = 54°
13 × 3.6 = 46.8°
15 × 3.6 = 54°
360°


flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Averages and Alligations Concepts
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon