The excess runoff hydrograph from a catchment area 10km2 due to a storm of 6 hrs duration has been observed to be triangular in shape. The peak flow is observed to be 10m3/s and the base length is 20 hrs. The rainfall excess in the catchment is
A
5.1 cm
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
3.6 cm
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
4.5 cm
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
2.5 cm
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B 3.6 cm Total runoff in m3=(12×20×60×60×10) =360,000m3 ∴Rainfall excess=(360,00010×106)m
= 0.036 m
= 3.6 cm