Question

The height of the down-sprue is 175mm and it cross-sectional area at the base is 200 mm2. The cross sectional area of the horizontal runner is also 200 mm2. Assuming no losses, the time (in seconds) required to fill a mold cavity of volume 106mm3 is

A
84.50
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
2.69
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
8.45
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
26.72
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 2.69
The given dimensions of mold box are shown in the figure.


The discharge velocity at the runner exit is determined as

v=2×9.81×0.175=1.8529 m/s=1852.9 mm/s

The filling time is given by

t=106200×1852.9=2.698s

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Order of Magnitude
PHYSICS
Watch in App
Join BYJU'S Learning Program
CrossIcon