The initial setting time of cement as specified in the Indian standards is:
A
>30 mins
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
< 30 mins
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
> 600 mins
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
< 600 mins
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is A >30 mins According to The Indian standards, in ordinary Portland cement, the initial setting time should not be less than 30 mins and the final setting time should not be more than 10 hours.