wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

The longest path in the network of PERT/CPM is identified as _________ path.

A
Logical
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
Critical
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
Continuous
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
Flow
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B Critical
The longest path in the network of PERT/CPM is identified as crritical path. In project management, a critical path is the sequence of project network activities which add up to the longest overall duration, regardless if that longest duration has float or not.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Limitation of Planning
BUSINESS STUDIES
Watch in App
Join BYJU'S Learning Program
CrossIcon