The maximum number of vehicles observed in any five minute period during the peak hour is 160. If the total flow in the peak hour is 1000 vehicles, the five minute peak hour factor (round off to 2 decimal places) is _____


  1. 0.52

Open in App
Solution

The correct option is A 0.52
Five minute peak hour factor

=flowinpeakhour605×peakflowduring5minute

PHF5=V60av605×V5av=100012×160=0.52