Question

The observed peak of flood during a 4 hour storm of 8 cm rainfall was, 500 m3/s. The average loss rate was 10 mm/hour and base flow was 50 m3/s. If there was rainfall of 12 cm in 4 hours on the same catchment, then discharge.

A
Increases by 950 m3/s
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
Decreases by 950 m3/s
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
Increases by 450 m3/s
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
Decreases by 450 m3/s
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C Increases by 450 m3/s
Peak unit hydrograph:

=Peak of flood hydrographBase flowp1ϕt=5005081×4
=112.5 m3/s

Now, the peak of new hydrograph

=Peak of unit hydrograph×R+Base flow

Where,
R=12ϕ×4=12(1×4)=8 cm
=112.5×8+50=950 m3/s

Hence, increases by
(950500)=450 m3/s

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Introduction and Basic Assumptions of Unit Hydrograph
HYDROLOGY & IRRIGATION
Watch in App
Join BYJU'S Learning Program
CrossIcon