The optimistic time (to), most likely time (tm) and pessimistic time (tp) (in days) of the activities in the critical path of a network are given in the format to−tm−tp in the figure below.
What is the probability (P%) of completing the project in 38 days if the non-exceedance probability factor (z) is tabulated below
Z | 1.0 | 1.04 | 1.1 |
(P%) | 84.13 | 85.25 | 86.43 |