Question

The optimistic time (to), most likely time (tm) and pessimistic time (tp) (in days) of the activities in the critical path of a network are given in the format totmtp in the figure below.


What is the probability (P%) of completing the project in 38 days if the non-exceedance probability factor (z) is tabulated below

Z 1.0 1.04 1.1
(P%) 84.13 85.25 86.43

A
85.25
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
14.75
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
90.32
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
9.68
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 14.75
Total standard deviation, (σt)=σ2pQ+σ2QR+σ2RS+σ2ST

=(1596)2+(1176)2+(1066)2+(1576)2

=1+(23)2+(23)2+(43)2=1.915

z=TsTEσ=38401.915=1.04

When z= 1.04, P = 85.25%

Therefore, for z=1.04; P%=10.8525=14.75 %

flag
Suggest Corrections
thumbs-up
1
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon