The pie-chart given in Fig. 25.17 represents the expenditure on different items in constructing a flat in Delhi. If the expenditure incurred on cement is Rs 112500, find the following:


(i) Total cost of the flat.
(ii) Expenditure incurred on labour.

Open in App
Solution

(i) Expenditure incurred on cement = Central angle of the corresponding sector × Total cost360°
Total cost of the flat = 360° × 11250075° = Rs 540000

(ii) Expenditure incurred on labour = Central angle of labour sector × Total cost360°
= 100° × 540000360°= Rs 150000