The power system having 60 buses, 8 of them are generator buses and remaining are load buses. 6 load buses are having voltage constraint and become divergent at the first iteration. The size of Jacobian matrix is
A
110 × 110
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
111 × 111
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
105 × 105
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
120 × 120
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C 105 × 105 Total number of buses = 60
Generator buses including slack bus = 8
Number of PV buses = Generator bus - 1 slack bus
Number of PV buses = 8 - 1 = 7
6 load buses are having voltage constraint (fixed voltage). So these buses will be treated as PV buses.
Total number of PV buses = 7 + 6 = 13
Total number of load buses (PQ) = 60 - 13 - 1 (Slack bus)
Number of PQ buses = 46
size of Jacobian = (2 × PQ + PV)×(2 × PQ + PV)
size of Jacobian = (2 × 46 + 13)×(2 × 46 + 13) = 105×105