Question

The pre-fault voltage are 1.0 p.u. at all buses. The system was unloaded prior to the fault.
A solid 3 phase fault takes place at bus 2.
The post fault voltages at buses 1 and 3 in per unit respectively are

A
0.24, 0.63
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
0.31, 0.76
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
0.33, 0.67
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
0.67,0.33
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 0.67,0.33
0.67, 0.33

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Z-Bus Building Algorithm
POWER SYSTEMS
Watch in App
Join BYJU'S Learning Program
CrossIcon