Question

The proposed dam shown in the figure is 90 m long and the coefficient of permeability of the soil is 0.0013 mm/second. The quantity of water (m3) that will be lost per day by seepage is (rounded to the nearest number):

A
55
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
57
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
59
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
61
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 57
Given,

K = 0.0013 mm/second

= 0.11232 m/day

HL=9 m

Nf=5

Nd=8

We know that,

q=KHLNfNd

=0.11232 ×9×58

=0.6318m3day/m

Total seepage loss,

Q = q ×Length of dam

= 0.6318×90

=56.862 m3/day

Hence, the correct option is (b).

flag
Suggest Corrections
thumbs-up
5
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Flow Nets
SOIL MECHANICS
Watch in App
Join BYJU'S Learning Program
CrossIcon