The rates of working of A and B are in the ratio 3 : 4. The number of days taken by them t6:1 finish the work are in the ratio
(a) 3: 4
(b) 9 : 16
(c) 4 : 3
(d) 16 : 9
Akbar can finish a work in 20 days and Surya can finish the same work in 80 days. If Surya and Akbar both work together, then find the total number of days taken by them to complete the work.