wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

The repair work of an overhead bridge was to be completed in 5 days time. 30 men were put on the job. After 3 days, it was found that only half the work could be completed. How many more men should be put on the job so that the work is completed as per the schedule?

A
12
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
18
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
15
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
20
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 15
30 men completed half of the work in 3 days. Remaining half of the work is to be completed in 2 days by X men, say
45 men can complete 12 of the work in 2 days
15 more men are required so that the work is completed as per schedule.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Speed-Distance-Time
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon