Question
The table gives details of an assembly line.
Work station
I
II
III
IV
V
VI
Total task time at the workstation (in minutes)
7
9
7
10
9
6
What is the line efficiency of the assembly line?
A
85%
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
80%
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
75%
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
70%
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is
B
80%
Total time used = TWC
=
7
+
9
+
7
+
10
+
9
+
6
= 48 min
T
c
=
Cycle time = 10 min
No. of workstation = 6
Line efficiency
=
T
W
C
n
×
T
c
×
100
=
Total time used
No. of workstation
×
cycle time
×
100
=
48
6
×
10
×
100
= 80%
Suggest Corrections
0
Similar questions
Q.
The table gives details of assembly line
Work station
1
2
3
4
5
6
Total task time
(Minutes)
15
10
12
13
15
9
The line efficiency of the assembly line is
Q.
In an assembly line for assembling toys, five workers are assigned tasks which take times of 10, 8, 6, 9 and 10 minutes respectively. The balance delay for line is
Q.
Draw a number line and represent each of the following on it:
(i)
5
+
-
2
(ii)
-
9
+
4
(iii)
-
3
+
-
5
(iv)
6
+
-
6
(v)
-
1
+
-
2
+
2
(vi)
-
2
+
7
+
-
9