The time cost curve for a project that is crashed is given in the figure. The project cost includes indirect cost per day. from the graph the minimum differencebetween crash cost per day and indirect cost per day is _____ (Rs.)



A
5
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
15
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
20
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
10
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 10
(Total cost)period(tr)=(Previous cost)ti+(Crashed cost)tfti(Indirect cost)tfti

The smallest raise occurs when the project is crashed from D to E and the difference between crash cost per day and indirect cost per day is minimum here = project cost at E project cost

D=95009490=10

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Introduction and Total Cost of the Project
OTHER
Watch in App
Join BYJU'S Learning Program
CrossIcon