There are 5 jobs and 2 machines in a product system.

JobABCDEMilling (min)54876Drilling (min)392410

What will be the minimum time required to complete all the jobs ?

A
32 min
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
42 min
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
36 min
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
30 min
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 32 min
Using Johnson't rule

Sequence - B - E - D - A - C


So, Minimum time to complete all the jobs = 32 min

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Instinct Tagging Conditioning and Imitating
BIOLOGY
Watch in App
Join BYJU'S Learning Program
CrossIcon