There are two 10 MVA generators of subtransient reactance 15% each and one 5 MVA generator of subtransient reactance 12%. The generators are connected to the station busbars from which load is taken through three 5 MVA, step up transformers each having reactance of 8%. The maximum fault MVA at LV side is _____ MVA.
- 175.4