Thirty men can complete a work in 36 days. In how many days can 18 men complete the same piece of work?


A

48

No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

36

No worries! We‘ve got your back. Try BYJU‘S free classes today!
C

60

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D

72

No worries! We‘ve got your back. Try BYJU‘S free classes today!
E

None of these

No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C

60


Required number of days =(30×36)/18=60