Thirty men were engaged to construct a road in 2 months. But 6men did not come to work at all. How many days will it take to construct the road?

( Assume that 2 months =60 days)


Open in App
Solution

Given that 30 men were engaged to construct a road in 2 months.

We know that,

2 months =60 days

Therefore,

30 men were engaged to construct a road in 60 days

Number of days required by 1 man to construct same road =30×60days=1800days

Since 6men did not come to work at all.

Number of men engaged in work =30-6=24

Number of days required by 24 men to construct same road =180024days=75days

Hence, it will take 75days to construct same road if 6men did not come to work at all.


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Joint Variations
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon