Three men paint a house in days. How many days do men take to do the same?
Finding the time taken by 30 men to paint house
Given that, men paint a house in days.
Now, we have to find the number of days, when men take to do the same work.
Let be the no. of days by men.
As we know the number of men and number of days is indirectly proportional to each other. Because, if the number of men increases, the days will decrease.
Hence, days is required to do the same work by men.