Three people A, B and C can do a job alone in 10 days, 12 days and 15 days respectively. In how many days they can finish the job working together?
A
4 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
72 days
No worries! Weāve got your back. Try BYJUāS free classes today!
C
6 days
No worries! Weāve got your back. Try BYJUāS free classes today!
D
213 days
No worries! Weāve got your back. Try BYJUāS free classes today!
Open in App
Solution
The correct option is A 4 days Amount of work that can be done in a day by A, B and C are 110,112 and 115 respectively.
One day worth of work that can be done if they work together is =(110+112+115)=1560=14 ∴ Time required to complete the job =114=4days.