wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

Three vendors were asked to supply a very high precision component. The respective probabilities of their meeting the strict design specifications are 0.8, 0.7 and 0.5. Each vendor supplies one component. The probability that out of total three components supplied by the vendors at least one will meet the design specifications is .
  1. 0.97

Open in App
Solution

The correct option is A 0.97
Probability that atleast one will meet the design speciication = 1 - probability that no will meet the design specifications
=1(10.8)(10.7)(10.5)
=1((0.2)(0.3)(0.5))
=0.97

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Birth of Sikhism
HISTORY
Watch in App
Join BYJU'S Learning Program
CrossIcon