Three women or four girls can build a well in 62 days. Find how many days will it take for 12 women and 15 girls to build the well.
3 Women = 4 Girls. They both can finish the work in 62 days
G = 34W(12W + 15G) × D = 3W × 62 where D is the number of days(12W + 15 × 34W) = 934W934W × D =3W × 62D = 8 days
G =34W
(12W + 15G) D = 3W 62 where D is the number of days
12 W + 15 × 34 W=934W
934WD = 3W 62
D = 8 days