CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

Three women or four girls can build a well in 62 days. Find how many days will it take for 12 women and 15 girls to build the well.

A
10
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
12
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
8
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
9
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 8

3 Women = 4 Girls. They both can finish the work in 62 days

G = 34W(12W + 15G) × D = 3W × 62 where D is the number of days(12W + 15 × 34W) = 934W934W × D =3W × 62D = 8 days
G =34W

(12W + 15G) D = 3W 62 where D is the number of days

12 W + 15 × 34 W=934W

934WD = 3W 62

D = 8 days


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Speed-Distance-Time
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon