Question

Three workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours?


Open in App
Solution

Finding the workers needed to do the job in 12 hours:

3 workers do the job in 28 hours.

1 worker will take 3×28=84 hours.

Let the number of workers needed to do the job in 12 hours be x:

Then, x=8412=7

So, 7 workers will complete the job in 12 hours.

Therefore, 7-3=4more workers are needed.

Hence, 4 more workers are needed to do this job in 12 hours.