Question

To complete a work. A takes $$50 %moretimethanB.Iftogethertheytake18daystocompletethework,howmuchtimeshallB$ take to do it?

A
30 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
35 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
40 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
45 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 30 days
Let us consider the number of days B requires to complete the work =x days
So, number of days A requires to complete the work =x+(50/100)x=1.5x

We can calculate, work done by A in 1 day =1/1.5x=2/3x
And work done by B in 1 day =1/x

We know that the Number of days A and B together requires to do work =18 days
So, work done by both A and B in 1 day =1/18

2/3x+18x=1/18
5/3x=1/18
x=(5×18)/3
x=30

B requires 30 days to complete the work.

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon