To make one cubic meter of 1:2:4 by volume concrete, the volume of coarse aggregate required is
A
0.95m3
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
0.85m3
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
0.75m3
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
0.65m3
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B0.85m3 1m3 of dry concrete =1.54m3 of wet concrete M15=1:2:4=1+2+4=7 Dry volume of concreteWet volume of concrete=1.54
Volume of cement =1.54×17m3
Volume of cement =0.22m3
Volume of sand =1.54×27=0.44m3
Volume of aggregate =1.54×47=0.88m3□8.85m3