Today is day 22 on the production control calendar, and four jobs are on order as shown :

Job Due Date Workday
Remaining
A 28 8
B 26 2
C 24 2
D 30 12

Rank the jobs as per critical ratio technique.

A
ABCD
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
CDAB
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
DACB
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
CBAD
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C DACB
Job Time
Remaining
(DD-DN)
Work
Remaining
(LTR)
Critical ratio
CR=DDDNLTR
Priority
A

B

C

D
28-22=6

26-22=4

24-22=2

30-22=8
8

2

2

12
0.75

2.00

1.00

0.67
2

4

3

1

With the critical ratio, jobs would be assigned in the order of D, A, C and B.

Jobs A and D have critical ratios of less than 1, meaning that the orders will not be shipped on time unless they are expedited. Job C, with an index of 1, is the only job, "on schedule".

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
The Cost Curve
ECONOMICS
Watch in App
Join BYJU'S Learning Program
CrossIcon