Today is day 22 on the production control calendar, and four jobs are on order as shown :
Job | Due Date | Workday Remaining |
A | 28 | 8 |
B | 26 | 2 |
C | 24 | 2 |
D | 30 | 12 |
Job | Time Remaining (DD-DN) |
Work Remaining (LTR) |
Critical ratio CR=DD−DNLTR |
Priority |
A B C D |
28-22=6 26-22=4 24-22=2 30-22=8 |
8 2 2 12 |
0.75 2.00 1.00 0.67 |
2 4 3 1 |