Two cubical castings of the same metal and sizes of 2 cm side and 4 cm side are moulded in green sand. If the smaller casting solidifies in 2 mins, the expected time of solidifications of large casting will be
For cube 1, M1=236×22=824=13
For cube 2, M2=436×42=6496=23
Solidification time∝(VA)2
ts∝M2
Hence, we have
T1T2=M21M22
Given data:
T1=2min
⇒T2=2×(23)2×(31)2=8min