two painters were painting a house.X finished hiswork in 10 days.thesame amount of work was done by painter Y in 12 days.how much more work does painter X do in a day than painter Y
Open in App
Solution
Let the total work be 1
Then,Time taken by painter X to do 1 work=10 days
And the time taken by painter Y to do 1 work=12 days
Then, work done by painter X in 1 day=110
And work done by painter Y in 1 day=112
Then the work which is done more by painter X than painter Y in 1 day =110−112=160=0.167 (approx.)