Two workers P and Q working together completed a job in 10 days. If P worked four times as efficiently as he actually did and Q worked 23rd as efficiently as he actually did, the work would have been completed in 3 days. P alone could complete the work in:


A

12.5 days

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B

7.5 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
C

6.25 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
D

15 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A

12.5 days


Let P’s 1 day’s work = ‘x’ and Q’s 1 day’s work = ‘y’

Then, x+y=110 and 4x+23y=13

Solving, we get - x = 225 and y = 150

∴ P’s 1 day’s work = 225

So, P alone could complete the work in 252=1212 days


flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Basics of Percentages
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon