Under Merrick's multiple piece rate system, ordinary piece rate is given to workers whose level of performance is between ________ of the standard output.
A
0% to 100%
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
0% to120%
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
0% to83%
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
None of the Above
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C0% to83% Merrick's multiple piece rate is a modification of Taylor;s differential plan. In this method three price rates are used to calculate the wages:
1.Standard piece rate up to 83% of the standard output
2.10% above the standard rate if output is between 83%-100%
3.20% above the standard rate if output is more than 100%