Given : Volume of Cuboidal reservoir = 108 m3
Rate of pouring water into cuboidal reservoir = 60 litres/min
=601000m3/minute[∵1liter=11000m3]
∵60×601000m3 water filled in reservoir will take = 100060×60 hours
∴1m3 water filled in reservoir will take=100060×60 hours
∴108 m3 water filled in reservoir will take=108×100060×60 hours=30 hours
It will take 30 hours to fill the reservoir.