CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

What will be the correct sequence that minimizes the total elapsed time required to complete the following jobs on three machines

M1, M2 and M3 in the order M1M3M2?


A
S - P - T - R - Q
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
S - Q - P - T - R
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
Cannot be determined
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
T - P - R - S - Q
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A S - P - T - R - Q
Given that jobs are processed in machines in order of

M1M3M2

So, minimum of M1 Maximum of M3

Minimum of M2 Maximum of M3

Both the above conditions are satisfied for the above problem. This problem can be reduced to two machines problem by adding the processing times,

M1j+M3j and M2j+M3j for each job.


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
The Production Function
ECONOMICS
Watch in App
Join BYJU'S Learning Program
CrossIcon