Question

Which network technique includes planning, monitoring and controlling?

A
CPM
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
Zero-Base Budgeting
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
PERT
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
Both (a) and (c)
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C PERT
PERT is a variation on Critical Path Analysis that takes a slightly more skeptical view of time estimates made for each project stage. To use it, estimate the shortest possible time each activity will take, the most likely length of time, and the longest time taken if the activity takes longer time than expected. It involves basic network technique which includes planning, monitoring and controlling of projects.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Limitation of Planning
BUSINESS STUDIES
Watch in App
Join BYJU'S Learning Program
CrossIcon