Which of the following is most likely to occur where activity level is lower than that planned?
A
An over absorption of fixed production overhead.
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
A reduction in expenditure on fixed production overhead.
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
An increase in expenditure on fixed production overhead.
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
An under-absorption of fixed production overhead
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution
The correct option is D An under-absorption of fixed production overhead If overheads are under absorbed, that means that more actual overhead cost is incurred than expected, with difference being charged to expense as incurred.
When activity level is lower than the planned , there is an under absorption of overheads.