CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

Which of the following relations are incorrect about floats in CPM ?
1. Total float = Latest finish time - Earliest start time
2. Free float = Total float - Head event slack
3. Independent float = Total float - Head event slack - Tail event slack

A
3 only
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
2 and 3 only
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
1 and 2 only
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
1 only
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 1 only
Total Float is the amount of time by which an activity can be delayed from its early start date without delaying the project finish date.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Organisational Objectives
BUSINESS STUDIES
Watch in App
Join BYJU'S Learning Program
CrossIcon