Which of the following relations are incorrect about floats in CPM ?
1. Total float = Latest finish time - Earliest start time
2. Free float = Total float - Head event slack
3. Independent float = Total float - Head event slack - Tail event slack
A
3 only
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
2 and 3 only
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
1 and 2 only
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
1 only
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution
The correct option is D 1 only Total Float is the amount of time by which an activity can be delayed from its early start date without delaying the project finish date.