Which of the following would not be an appropriate procedure for testing the general control activities of an information system?
A
Inquiries of a client personnel
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
Inspecting computer logs
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
Testing for the serial sequence of source documenyts
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
Examination of the organizational chart to determine the segregation of duties.
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C Testing for the serial sequence of source documenyts For testing general control activities of an information system, testing for serial sequence of source documents is not an appropriate procedure. It is done only to ensure if financial statements are prepared accurately having all necessary transactions recorded.