Which one of the following is NOT a decision taken during the aggregate production planning stage?

A
Scheduling of machines
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
Amount of labour to be committed
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
Rate at which production should happen
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
Inventory to be carried forward
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B Amount of labour to be committed
Amount of labour to be committed is NOT a decision taken during the aggregate production planning stage.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
The Multiplier Mechanism
ECONOMICS
Watch in App
Join BYJU'S Learning Program
CrossIcon