Which standard cost variance represents the difference between actual factory overhead incurred and budgeted factory overhead based on actual direct labour hours worked?
A
Volume variance
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
Spending variance
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
Efficiency variance
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
Quantity variance
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C Spending variance Total Factory overhead variance is the difference between the actual factory overheads and budgeted factory overheads based on the actual direct labour hours worked.