Work done for the process A→ B shown in the figure is
A
1 J
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
1.5 J
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
4.5 J
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
0.3 J
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution
The correct option is D0.3 J From the data given in the question
Pressure at state A is (P1)=10kPa
Pressure at state B is (P2)=30kPa
Volume at state A is (V1)=10×10−6m3
Volume at state B is (V2)=25×10−6m3
We know that, area under P - V curve with V-axis gives work done by the system.
Area under graph as shown in figure = Area of trapezium.
Thus,
Work done (W)=12(P1+P2)(V2−V1) =12×(30+10)×103×(25−10)×10−6
Work done (W)=0.3 J
Thus, option (d) is the correct answer.