wiz-icon
MyQuestionIcon
MyQuestionIcon
13
You visited us 13 times! Enjoying our articles? Unlock Full Access!
Question

Workability of concrete can be measured using slump, compaction factor and Vee bee time. Consider the following statements for workability of concrete.
(i) As the slump increases, the Vee bee time increases
(ii) As the slump increases, the compaction factor increases

Which of the following if TRUE?

A
Both (i) and (ii) are True
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
Both (i) and (ii) are False
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
(i) if True and (ii) is False
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
(i) is False and (ii) is True
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D (i) is False and (ii) is True
Slump is the subsidence of the specimen recorded in mm. As slump increases, water content increases

Workability increases
Compaction factor = Mass of partially compacted concrete/ Mass of fully compacted concrete

CF wil also increase
Vee bee time is the time required for transforming by vibration, a concrete specimen in the shape of a conical frustum into a cylinder. Hence, as workability increases, Vee bee time decreases.

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Solids,Liquids and Gases
SCIENCE
Watch in App
Join BYJU'S Learning Program
CrossIcon