wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

X and Y can do a piece of work in 72 days. Y and Z can do it in 120 days. X and Z can do it in 90 days. How many days does it take if all the three can work together?


A

100 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

150 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
C

60 days

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D

80 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C

60 days


Work done by (X + Y)’s in one day = 172(1)
Work done by (Y + Z)’s in one day = 1120(2)
Work done by (Z + X)’s in one day = 190(3)

(1) + (2) + (3) gives,
2(X+Y+Z)=172+1120+190=5+3+4360=12360=130
(X+Y+Z)s one day work =12×130=160
They will completed the work in 60 days.


flag
Suggest Corrections
thumbs-up
7
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Inverse Variations
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon