X and Y can do a piece of work in 72 days. Y and Z can do it in 120 days. X and Z can do it in 90 days. How many days does it take if all the three can work together?
60 days
Work done by (X + Y)’s in one day = 172…(1)
Work done by (Y + Z)’s in one day = 1120…(2)
Work done by (Z + X)’s in one day = 190…(3)
(1) + (2) + (3) gives,
2(X+Y+Z)=172+1120+190=5+3+4360=12360=130
∴(X+Y+Z)′s one day work =12×130=160
∴ They will completed the work in 60 days.